BLOG – Bridge Segments Over Westshore/Gandy Blvd. Intersection

Selmon Extension crews continue setting concrete segments, just hovering over pier ten at the Westshore/Gandy Boulevard intersection. Crews set the very first bridge segment back in February. As they set the segments, concrete fin installations won’t be too far behind. Once they reach the intersection, there will be around 200 segments in place and seven fins constructed. Each pier takes about two to three weeks per span (23 segments) between pier columns to set in place and be post-tensioned together. A temporary detour will be implemented. We will inform the public once we get specific details.