July 18, 2019 Kym Graves

BLOG – Casting Yard Update

Selmon Extension crews are approaching towards the half-way point of casting concrete bridge segments. More than 225 segments are currently cast and placed at the project’s offsite casting yard. Crews average around nine to ten per week. It will take roughly 750 concrete segments to complete the new bridge to the east interchange.