BLOG – Segment Launching Gantry (Update)

 

The segment launching gantry is moving closer to a very busy intersection. Selmon Extension crews will hit the milestone to the Westshore/Gandy Boulevard intersection, with around 200 segments in place later this fall.

Crews placed the first segment back in February of this year. Once they reach past Pier 10, they’ll have to temporarily shut down the intersection at night to set segments. As we get closer to that operation, we’ll be sure to provide you with advance notice.

 