Media Alert
January 26, 2018
Contact Information:
Mellisa McColley, Project Information Officer
[email protected]
813-613-2306
Tampa, FL Crews continue preconstruction activities on the Selmon Extension
Beginning Sunday, January 28, 2018 through Friday, February 2, 2018 short intermittent lane closures may occur along Eastbound and Westbound Gandy Boulevard to allow contractors to complete utility locates in the area.
Construction activities that will not impact traffic include relocating utility poles, the removal of roots and stumps, excavation and erosion control to prepare for the construction and maintenance of the highway and for the safety of he traveling public.
Please be reminded that both the Gandy Park South on the Southside of Gandy Boulevard and the Al Palonis Park on the north side of Gandy Boulevard are closed for the duration of the Selmon Extension construction. The Gandy Boat ramp will remain open. Thank you for your patience and understanding.
Please watch out for sudden stops, merging traffic and work zone operations.
For more information, call 813.613.2306 or email [email protected]
###